Completed projects

TUŁOWICE I/ II/ III SOLAR PARKS

Vortex Energy Polska - Park solarny Tułowice

December 2018 three new photovoltaic investments were commisioned. They are located in Opole voivodeship.

In each solar farm 3 150 photovoltaic panels and 15 inverters were installed. That gives 0,882 MW of installed power for each investment.

All three projects won regular auction for electricity sales from RES, organizaed in 2016 by URE.

Location: Opolskie province, Niemodlin municipality
Date of putting into service: 12/2018
Total installed power: 0.882 MW (each of the 3 projects)
Estimated annual production: 919 MWh (each of the 3 project)
Technical infrastructure: 3150 photovoltaic panels, 15 inverters (each of the 3 projects)
Additional information:

We have planned, developed, prepared projects for ERA auctions for the sale of energy from RES and we developed the projects. We covered the power plants with our own technical management.