News
2018 is the year of new solar projects
In 2018, Vortex Energy Polska expanded its portfolio of completed solar parks by 5 new projects located in Zachodniopomorskie, Łódzkie and Opolskie provinces.
Completed projects:
– ES Kraśnik Koszaliński – commissioning in April 2018, installed capacity: 0.988MW;
– ES Tułowice I / ES Tułowice II / ES Tułowice III – commissioning in December 2018, installed capacity of each investment: 0.882 MW;
– ES Piątek – commissioning in December 2018, installed capacity: 0.63 MW.
Each of the projects won the ERA auction for the sale of energy from RES at the end of 2016, which gave the green light to start construction works. Additionally, ES Piątek and ES Kraśnik Koszaliński projects are subsidized by European Funds.